Monday, January 14, 2013

Union Pacific Track Repair


This is just a reminder of the scheduled closures of the railroad crossings in our city. 
Union Pacific (UP) began work on their track renewal project in Fort Worth on January 4, 2013.  The project includes replacement of the north mainline rail, crossties, and rock ballast, as well as, the renewal of each roadway crossing.  UP expects to reach Forest Edge Drive in Arlington on January 16, as it moves east.  Below are the anticipated dates of closure for the roadway crossings in Arlington:
Street Name
Approx.
Closure
Approx.
Opening
Bowen Road
1/16
1/19
Davis Drive
1/17
1/20
Cooper Street
1/18
1/25
North Center Street
1/18
1/22
Mesquite Street
1/18
1/22
Collins Street
1/19
1/23
Stadium Drive
1/20
1/23
Great Southwest Parkway
1/21
2/3















Each roadway closure will last 3-4 days to replace the pads and approaches, except Cooper Street which will remain closed for 6-7 days due to the width of the roadway.  UP has committed to have Bowen Road re-opened before Collins Street closes, and Davis Drive re-opened before Stadium Drive closes.  Operations are expected to be completed in Arlington on January 23, with the exception of Great Southwest Parkway, which is expected to be closed for approximately two weeks due to UP’s work schedule.

2 comments:

  1. The schedule has changed.

    http://www.star-telegram.com/2013/01/15/4550204/plans-for-arlington-rail-crossing.html

    ReplyDelete
  2. Yes there has been a small change to the crossing closures. On Monday evening UP announced that they were only going to close Bowen Road for four hours on the 17th. They are going to accomplish the track repair at a later date at that crossing. This information was given out at the meeting in Council Chambers as a result of a request by the city.